LFO 2028 Project
Welcome! Here you will find everything you need to know about our school relocation project, including the latest news, surveys, an FAQ section, and much more. Please check back regularly for updates and opportunities to get involved.
Our Path to 2028
Approval of zoning change
Site visit and presentation: June 11
First decision: August 13
- Public hearing: within 6 weeks after the first decision
Approval target: fall 2026
Status: on schedule
Second half of 2025 / First half of 2026
Building permit
Detailed building design
Preparation of permit application file
Approval of construction plans
Status: scheduled for early fall 2026
Second half of 2026 / First half of 2027
Construction
Selection of service providers
Construction phase
Final project approval
Status: not started
Second half of 2027 / First half of 2028
Relocation of the LFO to Fornebu
- Choice of moving company
- Layout of rooms and furniture
- Moving
Status: not started
Second half of 2028
2e semestre 2025 / 1e semestre 2026
Approbation du changement de zonage
Chargé de dossier municipal désigné
Réunions de lancement avec la municipalité commencées en octobre
Objectif d’approbation : été 2026
Statut : dans les délais
2e semestre 2025 / 1e semestre 2026
Approbation du changement de zonage
Chargé de dossier municipal désigné
Réunions de lancement avec la municipalité commencées en octobre
Objectif d’approbation : été 2026
Statut : dans les délais